KYIV. Sept 4 (Interfax-Ukraine) – DTEK Energy Holding completed another major overhaul of a 200 MW power unit at one of its thermal power plants ahead of schedule.
As noted in a report of the holding on its Telegram channel on Saturday, this is the second power unit, which it managed to add to the power system within a week.
“As a result, we add 390 MW of power Ukraine’s energy strength,” DTEK said.
As reported, as of the end of August, DTEK announced the completion of scheduled repairs of 27 TPP power units by the end of the year, nine of which had already been repaired, and seven were under repair at that time.